Re: [PATCH] Fix org-agenda-skip-scheduled-if-deadline-is-shown bug


From: Morgan Smith
Subject: Re: [PATCH] Fix org-agenda-skip-scheduled-if-deadline-is-shown bug
Date: Tue, 02 Jan 2024 15:25:58 -0500
User-agent: Gnus/5.13 (Gnus v5.13)

Ihor Radchenko <yantar92@posteo.net> writes:

> Morgan Smith <Morgan.J.Smith@outlook.com> writes:
>
>> lisp/org-agenda.el (org-agenda-get-scheduled): Consolidate deadline
>> fetching code.  Don't check if deadline is shown when
>> 'org-agenda-skip-scheduled-if-deadline-is-shown' has a value of
>> 'repeated-after-deadline'.
>>
>> Currently when 'org-agenda-skip-scheduled-if-deadline-is-shown' has a
>> value of 'repeated-after-deadline' then there is no effect.  This is
>> because when 'org-agenda-get-scheduled' is run on later dates, the
>> previous deadlines are not put in 'deadline-pos'.
>
> May you please provide a detailed reproducer demonstrating the bug you
> are trying to fix? Such reproducer could be a basis of a new test.

See a detailed reproducer attached to this mail.  It has a task defined
as this:

* TODO task
SCHEDULED: <2017-03-06 Mon +2d> DEADLINE: <2017-03-10>

Running said reproducer currently fails as follows (the numbers are the
days of the month).

(string-equal
"06\nScheduled: task\n08\nScheduled: task\n10\nScheduled: task\nDeadline:  
task\n"
"06\nScheduled: task\n08\nScheduled: task\n10\nScheduled: task\nDeadline:  
task\n12\nScheduled: task\n")


As you can see, we expect to not see anything scheduled after the
deadline if 'org-agenda-skip-scheduled-if-deadline-is-shown' is set to
'repeated-after-deadline', however, we actually see that things continue
to be scheduled.  Hence the bug is that that option currently does
nothing.

Attachment: 0001-Testing-Add-tests-for-org-agenda-skip-scheduled-if-d.patch