[Top][All Lists]
[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
[status report]: GNU Herds' Human Resources
From: |
Davi Leal |
Subject: |
[status report]: GNU Herds' Human Resources |
Date: |
Wed, 24 Oct 2007 23:05:51 +0200 |
User-agent: |
KMail/1.9.5 |
Developers
----------
* Antenore, is working on the <div> based layout.
* Davi Leal, has a low productivity due to he has changed job.
* David Paleino, is overloaded with others FS projects.
* Klaus, is at Sudan in a military mission.
Advisers
--------
There is activity on this email list.
Translators
-----------
The translation process is on hold up to we finish the development.
Conclusion
==========
The lack of development activity is blocking the project. I hope show a draft
of the below task before Christmas:
task: HTTPS interface to some of the webapp administration operations
http://savannah.nongnu.org/task/?7339
The project moves slowly but surely.
- [status report]: GNU Herds' Human Resources,
Davi Leal <=